New concrete abutment wall beneath the repaired county bridge
← All projects
Infrastructure project

County Bridge Repair

Repair of an undermined county bridge abutment: excavating around the exposed timber piles, pouring a new reinforced footing and forming cast-in-place concrete walls to protect the structure.

Client
County road project
Scope
Bridge abutment repair
Problem
Erosion exposed the timber piles
Solution
New reinforced footing & walls
Method
Cast-in-place formed concrete
Before & after

From washed-out to built to last.

Before: the county bridge at the start of the job
Before: eroded rock and soil beneath the abutment
Before: timber piles exposed under the abutment
After: new concrete wall encasing the abutment
After: finished abutment wall beneath the bridge deck
After: new cast-in-place concrete corner
How the repair was done

Six steps to a stronger abutment.

  1. 01

    Assessment

    Erosion had washed out the rock and soil supporting the abutment, leaving the structure exposed.

    Washed-out rock under the bridge
    Erosion along the abutment
  2. 02

    Excavation

    The area around the abutment was dug out, exposing the timber piles for the repair.

    Excavating beneath the abutment
    Exposed timber piles
  3. 03

    Reinforced footing

    Rebar was tied in place for a new footing around the base of the piles.

    Rebar for the new footing
    Footing reinforcement along the piles
  4. 04

    Footing pour

    Concrete was poured to create a solid new footing beneath the abutment.

    Fresh footing concrete
    Footing with dowels for the new walls
  5. 05

    Forming the walls

    Formwork was built on the new footing to shape the concrete walls around the abutment.

    Wall forms going up
    Forms set along the abutment
  6. 06

    Pour & strip

    The walls were poured, the forms were stripped, and the site was backfilled.

    Pouring the end wall
    Forms in place before stripping
Your land. Your priorities. Your next step.

Let’s talk about what
you want to build.

In your 30-minute introduction, discuss your location, land, total project budget and must-haves. You do not need finished plans. A paid onsite consultation, if appropriate, is a separate next step.

Book an introductory call 30-minute introduction · Opens Calendly in a new tab.Prefer to call? (303) 563-9374